International Journal of Engineering Business
and Social Science
Vol. 1 No. 02, December 2022, pages: 80-85
e-ISSN: 2980-4108, p-ISSN: 2980-4272
https://ijebss.ph/index.php/ijebss
80
Analysis of Project Cost and Time Performance Control Using
Earned Value Method Analysis (EVM-A)
(Case Study of Concrete Road Construction Project)
James Thoengsal
1
, Miswar Tumpu
2
Fakultas Teknik Universitas Teknologi Sulawesi, Makassar
1
University, Makassar Graduate School Hasanuddin University, Makassar
2
Email:
jamesthoengsal@gmail.com
1
,
tumpumiswar@gmail.com
2
Submitted: Nov, 25th 2022 Revised: Dec, 13th 2022 Publication: Dec, 16th 2022
Keywords
Abstract
Performance; Cost; Time;
Construction; Performance
Construction projects have a high level of project complexity. Controls generally
separate between the accounting system for costs and the construction project
schedule system. The purpose of this research is to find out how Earned Value is
applied in project performance and to estimate project costs and time. This yield value
method includes Project Implementation Progress Reports and project financial
accounting data at the reporting date, then processed to obtain BCWS (Budgeted Cost
of Work Schedule), ACWP (Actual Cost of Work Performance), and
BCWP
(Budgeted Cost of
Work Performance). From the results
of control analysis and
forecasting
the total Estimate All Schedule (EAS) is 9 weeks, the total planning time
is 16 weeks. This means the project performance runs 4 weeks faster than the initial
plan time. where from the results of project performance evaluation control, it is
estimated that the project can be completed in its entirety in approximately 14 weeks
from the planned duration of 16 weeks or two weeks faster than the duration of the
initial plan and in terms of actual costs it is estimated that there will be an overall
savings of around 10.55% of the actual costs that have been realized.
1. Introduction
Construction projects have a high level of project complexity. Sometimes there are delays in
progress or cost overruns (Kaming et al. 1997). Controls generally separate between the accounting system
for costs and the construction project schedule system (AHMAD SUHAIMI, Nawawi, and PUTEH SALIN
2016). The cost accounting system generates performance reports and project cost predictions, while the
schedule system generates project completion status reports (Anbari
2003). The two reports complement each
other, but can
provide different information about project conditions, so a system is needed that is able to
integrate time and cost information (Baiden, Price, and Dainty 2006).
For this purpose, the concept of Result Value can be used as a performance tool that integrates cost
and time aspects (Bovea and rez-Belis 2012). Outlines/objects of project control can be identified, such
as time and schedule, the time spent being longer
or according to plan. Then, budget and costs, the budget
used exceeds the initial budget that has been determined or not.
IJEBSS e-ISSN: 2980-4108 p-ISSN: 2980-4272
IJEBSS Vol. 1 No. 02, December 2022, pages: 80-85
81
The formulation of the problem in this study is how is the performance of the Concrete Road
Construction project at Aryamas Residence Housing, Takalar Regency, South Sulawesi Province in terms
of time and cost and projected delays/progress.
The research objective to be achieved is to
examine whether the implementation of a project at the
time of reporting is still in accordance with the planned
budget and time schedule or not (Mabert, Soni, and
Venkataramanan 2003). Analyze the related elements in the form of achievement, cost and time
to find out whether the progress of project implementation is worth the part of the budget when measured
by the original plan, and estimate the total cost and time needed until the project is completed.
2. Materials and Methods
a. Types of
research
This research uses quantitative research methods. Where quantitative research is a type of research
that is more systematic, structured, specific,
and also well planned from the start to get a conclusion
(Miles
1990). Quantitative research places more emphasis on numbers which makes it more detailed and clearer.
In addition, the use of tables, graphs and diagrams makes it easier to read (Pinker 1990).
b. Time & Location of Research
The time referred to in this study is the overall
time of the course of research related to data collection
during research (Posada-Quintero and Chon 2020). The time needed by researchers to collect research
data is around 7 weeks, starting from March 12 2019 to April 25 2019. The research location in question
is the place where researchers get research data for this final project (Cypress 2018). Researchers
conducted
research on the Concrete Road Construction Project for
Infrastructure, Facilities and Utilities
(PSU) Public Houses Region II in the Aryamas Residence Housing District. Takalar, Prov. South Sulawesi.
Especially on 8
road sections, namely 1 section in Block C, 3 sections in
Block D, and 4 sections in Block
E.
c. Research Data
Sources
What is meant by the source of data in research
is the subject from which the data can be obtained. Data
sources are divided into two, namely primary data and secondary data (Shimwell et al. 2022). Primary data
is data obtained by researchers directly (first-hand). While secondary data is data obtained by researchers
from existing sources. In this study, data from both
sources were used. Primary Data Primary data is in the
form of observations of researchers to the project site. Secondary Data Secondary Data is data that is
already available so we just need to find and collect it. We can
obtain secondary
data more easily
and quickly
because
it is already available to the project executor. Secondary data in the form of: Cost Budget Plan
(RAB)/Implementation Cost Budget Plan (RAP), Schedule / (S-Curve), Detailed Engineering Design
(DED), weekly Reports.
Data analysis
From the data that has been obtained, then the work weight is calculated for each item. Then an
analysis of cost and time control is carried out using several approaches, namely:
a.
Calculation of Planned Cost or PV (Planned Value) or
Budgeted Cost for Scheduled Work (BCWS)
Planned Cost or BCWS by calculating the percentage of the work plan multiplied by the total project
cost that has been planned. Formula used:
𝐁𝐂𝐖𝐒
= %
𝐑𝐞𝐧𝐜𝐚𝐧𝐚
×
𝐁𝐀𝐂
……………..(1)
e-ISSN: 2980-4108 p-ISSN: 2980-4272 IJEBSS
IJEBSS Vol. 1 No. 02, December 2022, pages: 80-85
82
b.
Calculation of Result Value or EV (Earned Value)/Budgeted Cost for Work Performed (BCWP)
Percentage of completion/realization multiplied by the total planned real cost of the project. The formula
used is:
𝐁𝐂
𝐖
𝐏
=
%
𝐀
𝐤𝐭
𝐮
g
ulun
g
𝐥
×
𝐁
𝐀
𝐂
..............
(
2
)
c.
Calculation of Schedule Variance (SV)
SV calculation to find out the deviation between BCWP and BCWS values. If the SV value is positive,
then more project work has been carried out than planned. 28 Conversely, if a negative value indicates poor
job performance because less work is done than the planned schedule. According to (Desmi, 2011), the
formula used:
𝐒𝐕
=
𝐁𝐂𝐖𝐏
𝐁𝐂𝐖𝐒
=
𝐄𝐕
𝐏𝐕
…………………….(3)
d.
Calculation of Cost Variance (CV)
Calculation of CV to find out whether the project being carried out is still within the budget limit or
exceeds the budget. According to (Desmi, 2011), the formula used is:
𝐂𝐕
=
𝐁𝐂𝐖𝐏
𝐀𝐂𝐖𝐏
=
𝐄𝐕
𝐀𝐂
……………………(4)
e.
Calculation of Time Performance Index / Schedule Performance Index (SPI)
SPI calculation to compare the weight of work in the field and in planning. If the SPI value = 0 then the
project is on time, if the SPI value < 1 then the project progress is behind compared to the plan. And
conversely, if SPI > 1 then progress is faster than planned. As According to (Efe and Demirors 2019),
Formula used:
𝐒𝐏𝐈
=
𝐁𝐂𝐖𝐏
/
𝐁𝐂𝐖𝐒
=
𝐄𝐕
/
𝐏𝐕
…………..(5)
a. Calculation of Cost Performance Index (CPI)
CPI calculation by comparing the value of work that has been physically completed (BCWS) with the costs
incurred in the same period (ACWP). According to, the formula used is:
𝐂𝐏𝐈
=
𝐁𝐂𝐖𝐏
/
𝐀𝐂𝐖𝐏
=
𝐄𝐕
/
𝐀𝐂
………….(6)
IJEBSS e-ISSN: 2980-4108 p-ISSN: 2980-4272
IJEBSS Vol. 1 No. 02, December 2022, pages: 80-85
83
3. Results and Discussions
Research Flow Chart
Figure 1. Research Flowchart
Figure 3. Time-Based Result Value Concept Graph
i. Calculation of Cost Variance (CV)
Cost Variance (CV) is the difference between the value obtained after completing the work packages
and the actual costs during project implementation. Calculation of Cost Variance (CV) in Week 1 to Week 7
is as follows:
Figure 4. Integrated Cost and Schedule Variance Graph
ii. Calculating the Cost Performance Index (CPI)
e-ISSN: 2980-4108 p-ISSN: 2980-4272 IJEBSS
IJEBSS Vol. 1 No. 02, December 2022, pages: 80-85
84
The Cost Performance Index (CPI) is used to determine the cost status of the project. The calculation
for the CPI value obtained from week 1 to week 7 is as follows.
Figure 5. Graph of CPI and SPI Implementation Conditions
iii. Estimated Cost for remaining work (Estimate Temporary Cost/ETC) and time for remaining work
(Estimate Temporary Schedule/ETS).
Projection of delays/progress and Projection of Cost
Overrun/Cost Underrun at the end of the
Concrete Road Construction project at Aryamas Residence Housing District, Kab. Takalar, South
Sulawesi Province. From the cost aspect, the estimated cost for the remaining work (ETC) and the
estimated total project cost (EAC) obtained an EAC value of Rp. 312,087,921.25 while the BAC or RAB
value was Rp. 343,296,000.00, this means that at the end of
the project later it is estimated that there will be
a profit of Rp. 31,208,078.75 (9.09% of RAB). From the time aspect, the calculation of the estimated time
for remaining work
(ETS) is 2 weeks. Calculation of estimated total project time
(EAS) is (time used + ETS)
7 + 2 = 9 weeks, total planned
time is 13 weeks. This means the project performance runs
4 weeks faster
than the initial plan time
4. Conclusion
From the results of the application of the yield value method it is known that the results of the
review in the 7th week obtained BCWS = IDR 114,207,599.16; BCWP = IDR 336,878,761.28; ACWP =
IDR 306,254,055.74; Analysis of the Cost Performance Index (CPI) in the 7th week shows (CPI > 1) better
performance than planning while the Schedule Performance Index (SPI) shows a value (SPI > 1) in
terms
of work
performance earlier than
scheduled. And
it can be seen that the estimated final project cost / Estimate
At Complete (EAC) is IDR 312,087,921.25
with a planned budget of IDR 343,296,000.00. From the
calculation results, the estimated total project time/Estimate All Schedule (EAS) is 9 weeks, the total
planned time is 13 weeks. This means the project performance runs 4 weeks faster than the initial plan time.
From the results of the analysis of project performance evaluation control, it is estimated that the project can
be completed in its entirety in approximately 14 weeks from the planned duration of 16 weeks or two weeks
faster than the duration of the initial plan and in terms of actual costs it is estimated that there will be an
overall savings of around 10.55% of the actual costs that have been realized.
Thus the results of the analysis of performance evaluation control on the project show an increase
in time and cost performance which can be used as suggestions and considerations in implementing similar
projects in the future. In addition, the benefits of applying the Earned Value Management (EVM) method
are that it can assist in evaluating project performance and can show the amount of time/cost
performance
and deviations that occur in the project so
that control can be carried out before deviations get worse,
especially for project implementers, in this case the parties contractor. Overall, the biggest obstacle causing
the time deviation in the project in this study is due to the very limited number of local workers, so the best
solution is to increase the number of workers by sending workers from the Takalar district so that the project
IJEBSS e-ISSN: 2980-4108 p-ISSN: 2980-4272
IJEBSS Vol. 1 No. 02, December 2022, pages: 80-85
85
implementation schedule can return to normal and avoid delays and cost overruns. actual projects,
especially road projects in the area. Obstacles found during research where detailed actual data for actual
costs are relatively difficult to obtain in detail, this is also an obstacle in the application of the use of the
EVM method as an instrument for measuring cost performance and project time. Therefore, in future studies,
it may be necessary to have detailed financial administration management for the construction contractor
for each item of costs incurred during the implementation of the construction project as supporting data in
applying the EVM method.
5. References
Ahmad Suhaimi, Nazatul Syida, Anuar Nawawi, And Ahmad Saiful Azlin Puteh Salin. 2016.
“Impact of Enterprise Resource Planning on Management Control System and Accountants’ Role.”
International Journal of Economics & Management 10(1).
Anbari, Frank T. 2003. “Earned Value Project Management Method and Extensions.” Project
Management Journal 34(4):1223.
Baiden, Bernard K., Andrew D. F. Price, and Andrew R.
J. Dainty. 2006. The Extent of Team Integration within Construction Projects.” International
Journal of Project Management 24(1):1323.
Bovea, María Dolores, and Victoria Pérez-Belis. 2012. “A
Taxonomy of Ecodesign Tools for Integrating
Environmental Requirements into the Product Design Process. Journal of Cleaner Production
20(1):61–71.
Cypress, Brigitte. 2018. “Qualitative Research Methods: A Phenomenological Focus.” Dimensions of
Critical Care Nursing 37(6):3029.
Efe, Pinar, and Onur Demirors. 2019. “A Change Management Model and Its Application in Software
Development Projects.” Computer Standards & Interfaces 66:103353.
Kaming, Peter F., Paul O. Olomolaiye, Gary D. Holt, and Frank C. Harris. 1997. “Factors Influencing
Construction Time and Cost Overruns on High- Rise Projects in Indonesia.” Construction
Management & Economics 15(1):83–94.
Mabert, Vincent A., Ashok Soni, and M. A. Venkataramanan. 2003. “Enterprise Resource Planning:
Managing the Implementation Process.” European Journal of Operational Research 146(2):30214.
Miles, Matthew B. 1990. “New Methods for Qualitative Data Collection and Analysis: Vignettes and Pre‐
structured Cases.” Internation Journal of Qualitative Studies in Education 3(1):3751.
Pinker, Steven. 1990. “A Theory of Graph Comprehension.” Artificial Intelligence and the Future of
Testing 73:126.
Posada-Quintero, Hugo F., and Ki H. Chon. 2020. “Innovations in Electrodermal Activity Data Collection
and Signal Processing: A Systematic Review.” Sensors 20(2):479.
Shimwell, T. W., M. J. Hardcastle, C. Tasse, P. N. Best, H.
J. A. ttgering, W. L. Williams, A. Botteon, A.
Drabent, A. Mechev, and A. Shulevski. 2022. The
LOFAR Two-Metre Sky Survey-V. Second Data Release.” Astronomy & Astrophysics 659:A1.
© 2022 by the authors. Submitted
for possible open access publication
under the terms and conditions of the Creative Commons Attribution ShareAlike (CC BY SA) license
(https://creativecommons.org/licenses/by-sa/4.0/).